Central Library Development Project: Ottawa Public Library-Library and Archives Canada Joint Project
December 15, 2016
Report for Class D Construction Cost Estimate, Ottawa Public Library (Library Only), Exemplar Site City of Ottawa
December 14, 2016
Report for Class D Construction Cost Estimate, Ottawa Public Library (Library Only), Exemplar Site City of Ottawa
December 14, 2016
Ottawa Public Library – New Ottawa Central Library Master Program
December 14, 2016
Ottawa Central Library Project Cost Estimates: OPL-LAC Joint Facility and OPL Stand-alone Facility
December 14, 2016
Ottawa Central Library Project Cost Estimates: OPL-LAC Joint Facility and OPL Stand-alone Facility
December 14, 2016
Ottawa Central Library Development Project P3 Screening Assessment Report
December 14, 2016
Ottawa Central Library Development Project Site Evaluation Report
December 14, 2016
Ottawa Central Library: Inventory of Candidate Sites
December 14, 2016
Ottawa Public Library–Library and Archives Canada Joint Facility Master Program
December 14, 2016
Ottawa Central Library: OPL Stand-alone Facility Option
December 14, 2016
Central Library Development Project Relationship Framework
December 14, 2016
Ottawa Central Library Development Project OPL-LAC Partnership Assessment Report
December 14, 2016
Central Library Development Project Chronology
November 30, 2016
Soft Cost Assumptions Ottawa Public Library OPL and OPL/LAC, Exemplar Site (Site 8), City of Ottawa
November 21, 2016
Soft Cost Assumptions Ottawa Public Library OPL and OPL/LAC, Exemplar Site (Site 8), City of Ottawa
November 21, 2016
Report for Class D Construction Cost Estimate, Ottawa Public Library (OPL/LAC), Exemplar Site (Site 8), City of Ottawa
November 21, 2016
Report for Class D Construction Cost Estimate, Ottawa Public Library (OPL/LAC), Exemplar Site (Site 8), City of Ottawa
November 21, 2016
Summary Report: Public consultations in support of the Ottawa Central Library Development Project: In-person Consultation Sessions on the Functional Program
August 4, 2016
Summary Report: Public consultations in support of the Ottawa Central Library Development Project: In-person Consultation Sessions on the Functional Program
August 4, 2016
Central Library Development Project: Site Evaluation Process Report
July 12, 2016
Ottawa Central Library Public Engagement Framework
May 11, 2016
May 2016. A recommendation to the board to approve the public engagement framework for the Ottawa Central Library projec...
Ottawa Central Library Public Engagement Framework
May 11, 2016
May 2016. A recommendation to the board to approve the public engagement framework for the Ottawa Central Library projec...
Central Library Development Project
April 12, 2016
April 2016. A recommendation to the board to approve the initiation of the site selection process for the Central Librar...
March 8, 2016
Following discussion at the March 2016 meeting of the OPL Board, the Board approved a concurrent planning process for bo...
January 15, 2016
January 2016. Details of a potential partnership between OPL and LAC around the Central Library.
January 12, 2016
Nanos Research report on focus groups and surveys of more than 1,500 Ottawa residents about the Central Library. Includ...
November 26, 2015
November 2015. Operating and capital budget documents for Ottawa Public Library. This includes the $3.9M request for the...
September 15, 2015
September 2015. Details for submitting expressions of interest in the Central Library project as well as three addendums...
July 8, 2015
Complete listing of City of Ottawa 2015 – 2018 Term of Council Priorities including Strategic Initiative # 43 for the ...
July 7, 2015
July 2014. Detailed report outlining functional programming requirements, options for redevelopment, and preliminary co...
June 9, 2015
June 2015. Recommendation to the OPL Board to approve the option to build a new, 132,000 square feet Central Library in ...
May 20, 2015
May 2015. Detailed report by Library Strategies International outlining potential programs, features, best practices, tr...
May 19, 2015
May 2015. A map of the Central Area approved by OPL’s Board where a site for the Central Library will be located. Engl...
May 15, 2015
May 2015. Detailed business case by Grant Thornton on options for renewal, renovation, redevelopment, and a new build of...
April 15, 2015
April 2015. Approved four-stage implementation process for Central Library development. English only.
April 14, 2015
April 2015. The Board-approved strategic plan for the Ottawa Public Library for 2015-18. Includes the development of an ...
July 7, 2014
November 2012. Report recommending modernizing the Main branch in lieu of status quo or refreshing options. English onl...
December 9, 2013
December 2013. Final report summarizing feedback from the IMAGINE Campaign, an online ideas campaign about the future of...
June 15, 2012
July 2012. Nanos Research report on surveying of more than 1,400 Ottawa residents about the Main Library. English only.
May 14, 2012
May 2012. A report outlining facilities plans across OPL with the recommendation for renewal priorities for a nine-year ...
September 12, 2011
September 2012. Technical assessment of the Main Library building with recommendation for lifecycle repairs and maintena...

Request for Proposals (RFP No. 30018-90610-P01) for Professional Design Services for the Ottawa Central Library Project: PDF icon: document download for Request for Proposals (RFP No. 30018-90610-P01) for Professional Design Services for the Ottawa Central Library Project


All other documents and reports on the Central Library project can be found by searching the City of Ottawa's e-Agenda system. Select the Ottawa Public Library board as the meeting type.